Before ordering a freeze dryer from China, agree who manufactures it, the technical specification, acceptance tests, shipping scope and installation responsibilities.
Many sellers are trading companies. That is not automatically bad, but you should know who welds your chamber. Ask for a live video walk-through of the workshop, see machines in production, and request the business licence. A visit before signing is the strongest check if the order justifies it.
The quotation is not enough. A technical agreement attached to the contract should fix:
Agree on a factory acceptance test: pump-down to the specified vacuum, condenser temperature, shelf temperature control and a leak test. Witness it in person or by live video, and keep the recorded values; they become your baseline after installation.
When you write the technical agreement and agree the factory acceptance test, use this list. It does not set acceptance limits; record the values you actually measure.
| Requirement | Evidence to request | Acceptance record |
|---|---|---|
| Water capture per batch | The figure in the technical agreement, and the product it was sized for | Confirm that agreed figure stays in the technical agreement |
| Voltage and heat source | Site voltage, frequency and heat source (electric or steam) written into the technical agreement | Confirm those agreed details are written into the technical agreement |
| Vacuum | The specified pump-down / vacuum for the factory acceptance test | The pump-down value recorded at the factory acceptance test |
| Condenser temperature | The specified condenser temperature for the factory acceptance test | The condenser temperature recorded at the factory acceptance test |
| Leak test | An agreed leak test as part of the factory acceptance test | The leak-test result, kept as the baseline after installation |
Common practice is a deposit to start production and the balance before shipment, by bank transfer; letters of credit are often used for larger orders. Agree the Incoterm clearly, for example FOB or CIF from Qingdao, the major port closest to our factory in Shandong. Large chambers can need special containers, so confirm packaging and container type in the contract.
Agree the supply scope (machine, line or turnkey). Clarify whether an engineer will travel for installation and training, and who covers travel and visa costs. Check early which certifications or electrical standards your country requires, so the machine is built to them rather than modified later.
Our approach: we build in our own workshop, put every figure in the technical agreement, and welcome factory visits or live video inspections before you commit.